7. Mohit can complete a work in 50 days, whereas Anuj can complete the same work
40 days.
Find : () work done by Mohit in 20 days.
(ii) work left after Mohit has worked on it for 20 days.
(iii) time taken by Anuj to complete the remaining work.
Answers
Answered by
1
Answer:
1 work done by Mohit. in. 20days
work done by Anuj in 10 days