Computer Science, asked by akshikatiwari06, 1 month ago

7

Not yet answered

Marked out of 1

PFlag question

You have a Project 2010 schedule. You need to schedule the task Move to Production during weekends. What should you do?

Each correct answer represents part of the solution. Check all that apply.

Select one or more:

a. Assign the weekend base calendar to Move to Production task

b. Change the start date and finish date of the Move to Production

c. Create a base calendar with weekends as working days

d. Extend the working time of the resource to weekends​

Answers

Answered by navyanshchoudhary
1

Answer:

c) create a base calendar with weekends as working days

Similar questions