7) P alone can finish a job in 12 days while Q can do so in
16 days. With the help of R, they have finished the job in
4 days for a contract price of 1,200. How much should
R get out of it?
Answers
Answer:
R will get 500
Step-by-step explanation:
Given,
P alone can finish a job in 12 days
P=1/12
Q can do so in 16 days.
Q=1/16
With the help of R, they have finished the job in 4 days
P+Q+R=1/4
1/12+1/16+R=1/4
R=1/4-1/12-1/16
R=5/48
a contract price of 1,200
ratio between P,Q,R is
1/12:1/16:5/48
LCM=48
1/12*48:1/16*48:5/48*48
4:3:5
Let 4p:3p:5p are amounts of P,Q,R
total 4p+3p+5p=1200
12p=1200
p=100
R=5p
=5*100
=500
Given :-
- P alone can finish job in = 12 days.
- Q alone can finish in = 16 days.
- With the help of R, they have finished the job in 4 days for a contract price of 1,200.
To Find :-
- How much should R get out of it ?
Solution :-
LCM of 12 and 16 = 48 units = Let total work
so,
→ Efficiency of P = (Total work)/(Total days) = 48/12 = 4 units/day.
and,
→ Efficiency of Q = (Total work)/(Total days) = 48/16 = 3 units/day.
Now, Let us assume that , Efficiency of R is x units/day.
then,
→ 4(4 + 3 + x) = 48 units
→ 4 + 3 + x = 12
→ x = 12 - 7
→ x = 5 units/day .
Therefore, we can conclude that, they will get amount in the ratio of their efficiency .
hence,
→ Share of R = (5/12) * 1200 = Rs.500 (Ans.)
Learn more :-
Giri does 2/5 piece of work in 10 days. Ankit does 5/9 of the remaining work in 15 days and Gaurav finishes remaining wo...
https://brainly.in/question/21025557
Shivam alone can do a work in 12 days and Maanik alone can do it in, 15 days. Both started the work together and after w...
https://brainly.in/question/14687371