Math, asked by monjudas0, 1 day ago

7 people can do a work in 12 days, double the amount of work in 8 days, how many extra people will be needed?​

Answers

Answered by sharfoon422
0

Answer:

swipe up you I'll be get answers and make sure make my answer brainliest thanks again

Answered by sathyapriyalokeshh
1

Step-by-step explanation:

When 7 men complete a piece of work in 12 days, the work requires 7*12=84 man/days

Men required to complete the work in 8 days=84/8=10.5 Men

Men required to complete Double the work in 8 days=10.5*2=21 Men Additional Men required to complete Double the work in 8 days=21–7=14 men

please make me brainliest answer