7 people need 100 days to repair and paint heritage building if the job should be completed in 25 days how many more people need to be employed

Answers

Answered by Anonymous
12

We'll use Unitary Method in this case:-

 \frac{7}{100}   =  \frac{x}{25}  \\  = x = 28

Considering the number of people as x, 28-7 = 21 more people need to be employed.

_____________________________

Hope it helps you :D