Math, asked by sinhanisi7, 5 hours ago

7 soldiers can clear a Land-slided highway in 1 week working 10 hours a day.
How many additional hours must they work to clear the highway in 5 days?

step by step solve this and send​

Answers

Answered by Missmile
3

Answer:

Ok dear

Your answer is 4 hours each day

Step-by-step explanation:

First find out how much hours do these soldiers work

= 7 × 10 = 70 hours

In 5 days = 5 × 10 =

So extra hours are 70 - 50 =20

To finish work in 5 days they need to work 20÷5 =4 more hours each day.

HOPE IT HELPS

HAVE A GREAT DAY DEAR FRIEND