7. Twenty persons can do a piece of work in 16 days. How much more persons are required to finish the work in 10 days . Is answer 32
Answers
Answered by
1
Answer:
16 days - 20 persons
10 days-?
10days=more/less*RHS
=16/10*20
=32 PERSONS
=32-20=12 MORE PERSONS ARE NEEDED TO COMPLETE THE WORK