7 workers can fit a machine in 6 days .if 14 workers work.How much less time will be needed to further machine
Answers
Answered by
0
Answer:
3 days
Explanation:
7 workers = 6 days
14 workers = ______
[Men x days = total work]
Total work = 7x6
=42
14×days=42
days = 42/14
days=3 ans...