72 men are engaged for a task with a timeline given beforehand. It is found that in 38% of the given time
13
36% of the task is accomplished. How many additional men are to be engaged so that the timeline can be
met?
Answers
Given :- 72 men are engaged for a task with a timeline given beforehand. It is found that in 38% of the given time 36% of the task is accomplished. How many additional men are to be engaged so that the timeline can be met ?
Solution :-
given that, in 38% of the given time 36% of the task is accomplished.
So, we can say that,
- Time left = 100 - 38 = 62% .
- Work left = 100 - 36 = 64% .
now, we can say that, 72 men completes 36% of the task in 38% of the given time. we need to find how many men needed to complete left work 64% in left 62% of time.
we know that,
- Time ∝ (1/work done).
Let us assume that, Total x men completes rest of the work.
So, Applying chain rule we get,
→ 72 * 64 * 38 = x * 36 * 62
dividing both sides by 36,
→ 64 * 38 * 2 = 62x
→ 62x = 4864
dividing both sides by 62,
→ x ≈ 78 men .
Therefore,
→ Additional men to be engaged = 78 - 72 = 6 men (Ans.)
Hence, 6 additional men are to be engaged so that the timeline can be met.
Learn more :-
-एक ठीकेदार ने किसी काम को 24 दिनों में समाप्त करने का ठेका लिया। उसने 8 घटे ।दिन काम करनेवाले 120 लोगों को काम पर लगाया...
https://brainly.in/question/23392938
A and b can complete a work in 8 days working together. b alone can do it in 12 days after working for four days, b left...
https://brainly.in/question/3396738