Math, asked by aaranthaara, 6 months ago

72 men are engaged for a task with a timeline given beforehand. It is found that in 38. of the given time
met?
36% of the task is accomplished. How mny additional men are to be engaged so that the timeline can be​

Answers

Answered by amitnrw
2

Given :   72 men are engaged for a task with a timeline given beforehand.

It is found that  in 38% of the given time 36 % of the task is completed

To Find :  . How many additional men are to be engaged so that the timeline can be​ met

Solution:

Let say Total Work  = 100W   and to Be completed in  100D Days

Let say a Man do work  A in 1 Day

38% of the given time  = 38D says

Work Done  = 72A * 38 D

36 % of the task is completed  => Work Done = 36W

72A * 38 D  = 36W

=> AD  = W/76

Work Left  =  100W - 36W = 64W

Days Left = 100D - 38D  = 62D

Let say Men now = M

So Work done  = MA62D  

= 62M (AD)

= 62M ( W/76)

62M ( W/76) = 64W

=> M = 64 x 76 / 62

=> M = 78.45

As time line need to met so we need to round up men

=> M = 79

Additional Men Required = 79 - 72 = 7

Learn More:

20 men can complete a piece of work in 15 days. One man starts the ...

brainly.in/question/9066294

A work is completed such that on the nth day from the start n men ...

brainly.in/question/11508647

Similar questions