Math, asked by siddhartha899, 7 months ago


72 men do a piece of work in 250 days. In how many days will 30 men do the same
work?​

Answers

Answered by balamuralidharraju82
0

Step-by-step explanation:

72 men do a piece

work in 250 days

150 do the same work

think soooooo

Answered by Anonymous
11

Given :-

  • Men(M1) = 72
  • Days (D1) = 250
  • Men (M2) = 30

To Find :-

  • Days (D2) = ?

Solution :-

Making table :-

Mens | 72 | 30 |

Days | 250 | x |

Let, D2 be x ,

Cross multiplication, we get :

↪ 72 × x = 30 × 250

↪ x = 30 × 250 / 72

↪ x = 7500/ 72

↪ x = 104.16

↪.°. D2 = 104.16.

Hence,

  • The 104.16days will 30men do the same work.

Verification :-

Mens | 72 | 30 |

Days | 250 | 104.16 |

↪ Cross multiplication, we get :

↪ 72 × 104.16 = 250 × 30

↪ 7499.52 = 7500

↪7500 = 7500

Hence Verified !!