72 men do a piece of work in 250 days. In how many days will 30 men do the same
work?
Answers
Answered by
0
Step-by-step explanation:
72 men do a piece
work in 250 days
150 do the same work
think soooooo
Answered by
11
Given :-
- Men(M1) = 72
- Days (D1) = 250
- Men (M2) = 30
To Find :-
- Days (D2) = ?
Solution :-
Making table :-
Mens | 72 | 30 |
Days | 250 | x |
Let, D2 be x ,
Cross multiplication, we get :
↪ 72 × x = 30 × 250
↪ x = 30 × 250 / 72
↪ x = 7500/ 72
↪ x = 104.16
↪.°. D2 = 104.16.
Hence,
- The 104.16days will 30men do the same work.
Verification :-
Mens | 72 | 30 |
Days | 250 | 104.16 |
↪ Cross multiplication, we get :
↪ 72 × 104.16 = 250 × 30
↪ 7499.52 = 7500
↪7500 = 7500
Hence Verified !!
Similar questions