78 men can do a work in 140days ,In how many days will take 42men do the same work.
Answers
Answered by
1
Step-by-step explanation:
Answered by
0
Answer:
PLEASE MARK ME AS BRAINLIEST PLZZZZZZZ
Step-by-step explanation:
42 men can do a piece of work in 140/78×42=980/13=75 upon 5/13 days.