Math, asked by okokokff, 3 months ago

78 men do a work in 140 days. how many days will 42 men do the same work in?​

Attachments:

Answers

Answered by aanyasharma70ster
1

Step-by-step explanation:

42 men can do a piece of work in 140/78×42=980/13=75 upon 5/13 days.