8. 12 ᴩᴇʀꜱᴏɴꜱ ᴄᴀɴ ꜰɪɴɪꜱʜ ᴀ ᴩɪᴇᴄᴇ ᴏꜰ ᴡᴏʀᴋ ɪɴ 15 ᴅᴀyꜱ. ɪɴ ʜᴏᴡ ᴍᴀɴy ᴅᴀyꜱ ᴡɪʟʟ ᴛʜᴇ ꜱᴀᴍᴇ ᴡᴏʀᴋ ʙᴇ ᴄᴏᴍᴩʟᴇᴛᴇᴅ ʙy 20 ᴩᴇʀꜱᴏɴ
Answers
Answered by
1
Answer:
one person can finish = 12/15
= 2/5 days
20 persons can finish = 2/5 × 20
= 8 days
Answered by
0
Answer:
12 person can finish work in 15 days
20 person can finish work in=12*15/20
=9days
:)