8. 16 men can complete a piece of work in 24 days. In how many days can 12 men completes
the same piece of work?
(1) 30 days (2) 32 days (3) 36 days (4) Data inadequate (5) None of these
Answers
Answered by
2
Answer:
32 days
Step-by-step explanation:
16 m * 24=xm *12
x= 32 days