8. 44 men can finish a piece of work in 36 days.
How many men will be needed to finish it in
16 days?
Answers
Answered by
1
Answer:
It is in the inverse proportion
If number of men increases then time take to complete the work will decrease
So
Let 1 rupee be the wage per person per day
Then 44 men earn 44 rupees per day
So 44 men earn 44×36 rupees in 36 days
44×36 = 1584 (it is total worth of the work)
To complete in 16 days
1584/16 = 99
So to complete the work in 16 days 99 men are required
Answer is 99
Thank you
Answered by
1
Step-by-step explanation:
Number of men required to finish the work