8. 7 men and 8 boys can do a piece of work
29
in 2 days. 4 men and 12 boys can do
of
56
the same work in 1 day. In how many days
will I man do this work?
ас
Answers
Answered by
0
Answer:
Step-by-step explanation:
7m + 8b =1/2. work in a day-------(1)
4m + 12b=29/56. work in a day-------(2)
Multiply equation (1) by 12
Multiply equation (2) by 8
I. e, 84m + 96 b =6-
32m + 96 b =(29/7)
--------------------------
52m. =(13/7)
m =(13/7) = 1
--------- ----- work in a day
52. 28
A man can do work in 28 days