8. A and B can complete a piece of work in 5 days
and 10 days respectively. They work together
and after 2 days C joins them. The work is
now completed in 1 day. In how many days
can C alone do the work? PLZ ANSWER THE QUESTION I WILL MARK THE ANSWER AS BRAINLIST
Answers
Answered by
1
Step-by-step explanation:
a=5days
b=10 days
and b LCM is 10
the whole work is 10
a=10/5= 2 work in a day
b=10/10 1 work in a day
a+b=3
they have two days work 3*2=6 work in 2 days remaining work is 4
now c join them
a+b+c=4
3+c=4
c=4-3
c=1
c efficiency is 1
and the whole work is 10
10/1=10
In 10 days c complete the whole work.
I hope it will be helpful to you if yes give me a like.