8. A and B can do a piece of work in 20 days and 30 days respectively. B started the work and after 5 days A joined. Find the total time taken to complete the work.
Answers
Answered by
0
Answer:
A's one-day work =1/30
B's one-day work = 1/20
A+B ‘s one-day = 1/30+1/20=2+3/60=5/60=1/12
So A and B work together and complete by 12 days
B leaves 5days before complete the work
So they worked together for 7 days
7*1/12=7/12
Total work = 1–7/12=5/12
Remaining work = 5/12
A finishes remaining work,
Full work in 30days
1= 30
5/12= x
x= (5/12)*30=150/12=12.5
So A takes 13 days to complete remaining work.
Total time to complete the work is 7+13= 20days