8. A and B can finish a piece of work in 16 days and 12 days respectively. A started the work
and worked at it for 2 days. He was then joined by B. Find the total time taken to finish the work?
Answers
Given that A finishes the work in 16 days.
A finishes 1/16 of the work in one day.
A had worked for two days= 2*1/16 = 1/8
the work left after A has worked for two days = 1- 1/8 = 7/8
B finihses the work in 12 days
in 1 day B finishes 1/12 of the work.
A and B togeher in one day can finish= 1/16+1/12 = (3+4)/48= 7/48 of work
A and B together can complete the remaining work= (7/8) / (7/48)= 7*48/8*7 = 6 days.
therefore total time taken = 2 days by A alone + 6 days by both Aand B = 8 days
☆☆
Average work=48(LCM of 16 and 12)
A does 48 work in 16 days
In 1 day 48/16=3work
B does 48 work in 12 days
In 1 day 48/12=4work
A done work for 2 days
So,work done by A 8n 2 days=2×3=6
Remaining work is 42
A+B together can do 7 work in a day
Thus,42/7=6days
Total days 6+2=8days.
☆☆
☆☆