Math, asked by rohithyprash, 7 months ago

8. A and B can finish a piece of work in 16 days and 12 days respectively. A started the work
and worked at it for 2 days. He was then joined by B. Find the total time taken to finish the
work.
it
i1​

Answers

Answered by hemanthnisme11
2

Answer:

8 days.

Step-by-step explanation:

A can finish (1/16)th portion of the work in 1 day. In 2 days he completes 1/8th portion of the work.

let us assume they work together for x days and complete the work.

(1/16 + 1/12) x= (7/8)

(7/48)x= (7/8)

x=6

Total time taken to complete the work is x+2=8 days.