8. A and B can finish a piece of work in 6 days and 4
days respectively. A started the work and worked
for 2 days. He was then joined by B. Find the
total time taken to finish the work.
Answers
Answered by
1
dont know
so sooooorrrrrrryyyyyyy
Answered by
1
Answer:
18/5
Step-by-step explanation:
Work done by A in one day = 12/6 = 2units
Work done by B in one day = 12/4 = 3 units
A working for 2 days will do 2*2 units = 4 units of total work
Remaining work = 12–4 = 8 units
Since B has joined A after this both will together finish remaining work = 8/2+3 = 8/5 days
Total time taken = A's 2 day work + 8/5 days
= 18/5 days