8. A and B can finish a piece of work in 6.
days respectively. A started the wo
for 2 days. He was then joined by B.
total time taken to finish the work.
1 By B. Find the total time to finish work.
please give me the answer
Answers
Answered by
2
Answer:
A started the work and worked for 2 days. He was then joined by B. Find the total time taken to finish the work. ... for 2 days,. So A will complete 2*1/6 = 1/3 rd of work.
Answered by
0
Answer:
Answer:A started the work and worked for 2 days. He was then joined by B. Find the total time taken to finish the work. ... for 2 days,. So A will complete 2*1/6 = 1/3 rd of work.