8. A, B and C can do a piece of work in 10 days. A alone can do it in 40 days, and B alone can do it in 30
days. In how many days will C alone do the same work ?
Answers
Answered by
2
Answer:
- A, B and C can do piece of work in 10 days so they can do 1/10 part of work in a day
- A alone can do same work in 40 days so A can do 1/40 part of work in a day B alone can do it in 30 days so B can do 1/30 part of work in a day
Let the days taken by C be x
1/10=1/40+1/30+1/x
1/10=7/120+1/x
1/10-7/120=1/x
12-7/120=1/x
5/120=1/x
1/24=1/x
therefore C can do 1/24 in a day
so C can do whole piece of work in 24 days
bbbbgohain:
last part ????
Answered by
1
Answer:
24
Step-by-step explanation:
A+B+C=10 effi=120/10=12
A =40 LCM=120 effi=120/40=3
B =30 effi=120/30=4
Effi of C=12-(3+4)=5
C can do the work in=120/5=24days
This is the short method n time saving also..
I hope u like this method