8. A pond will be dug in our locality. 24 men need 12 days to cut that pond. Let's
find out the proportion and find relation how many men will be needed to dig that
pond in 8 days.
Answers
- 24 men took 12 days to cut the pond
- Number of men required to finish the work in 8 days
- Let the total men required to finish the work in 8 days be "x"
Method I
➠
➠
➠
➠
➠
➠
As "x" men can finish the work in 8 days
So,
➜
➜
➨ x = 36 men
- Hence , 36 men can finish the work in 8 days
Method II
〚 We can clearly observe that when the number of men will increase the days required to finish the work will decrease. Therefore it is a case of inverse proportion 〛
So,
- Let the number of men required to finish the work in 8 days be "x"
➜ 24:x = 8:12
➜
➜
➜ 288 = 8x
➜
➨ x = 36
- Hence 36 men can finish the work in 8 days
- 24 men took 12 days to cut the pond
- Number of men required to finish the work in 8 days
Let the total men required to finish the work in 8 days be "x"
Method I
➠
➠
➠
➠
➠
➠
As "x" men can finish the work in 8 days
So,
➜
➜
➨ x = 36 men
Hence , 36 men can finish the work in 8 days
Method II
〚 We can clearly observe that when the number of men will increase the days required to finish the work will decrease. Therefore it is a case of inverse proportion 〛
So,
Let the number of men required to finish the work in 8 days be "x"
➜ 24:x = 8:12
➜
➜
➜ 288 = 8x
➜
➨ x = 36
- Hence 36 men can finish the work in 8 days