8. A works twice as fast as B. They work together and complete a job in 8 days how long
would A take to complete the job?
Answers
Answered by
0
Ratio of Rate of working of A & B = 2:1
Ratio of time taken is = 1:2
Let x day taken by A.
So,;2 day taken to work (
x
1
)
th
and 2x day by B
1 day →(
2x
1
)
th
1 day →
x
1
+
2x
1
=
2x
3
8 day →
2x
8×3
2x
8×3
=1
x=12 day
please mark me as brainliest