8. Chandan can do 1/ 6 part of a piece
of work in 8 days, then he will do 1/8
part of the work in :
(a) 9 days (b) 48 days
(c) 8 days (d) 6 days
Answers
Answered by
2
Answer:
8 days
is your answer
please mark me brainlist please
Answered by
8
Step-by-step explanation:
⅙ part of work is completed in 8 days
1 or whole part of work is completed in 8÷⅙ days
=8×6=48 days
⅛ part of work is completed in 1/8×48= 6 days (d)
please mark it as a brainlist answer
and thanks my answers