8 days for 12 men to construct a wall. how many men should be put on the job if it is required to be constructed in 6 days?
Answers
Answered by
96
Answer:
ᴀɴꜱᴡᴇʀ
ᴛɪᴍᴇ ᴛᴀᴋᴇɴ ʙʏ 12 ᴍᴇɴ ᴛᴏ ᴄᴏɴꜱᴛʀᴜᴄᴛ ᴀ ᴡᴀʟʟ = 8 ᴅᴀʏꜱ.
ᴛɪᴍᴇ ᴛᴀᴋᴇɴ ʙʏ 1 ᴍᴀɴ ᴛᴏ ᴄᴏɴꜱᴛʀᴜᴄᴛ ᴀ ᴡᴀʟʟ = 12×8 ᴅᴀʏꜱ
∴ ᴛɪᴍᴇ ᴛᴀᴋᴇɴ ʙʏ 6 ᴍᴇɴ ᴛᴏ ᴄᴏɴꜱᴛʀᴜᴄᴛ ᴀ ᴡᴀʟʟ =
6
12×8
ᴅᴀʏꜱ
=16 ᴅᴀʏꜱ
Answered by
15
Step-by-step explanation:
ANSWER
Time taken by 12 men to construct a wall = 8 days.
Time taken by 1 man to construct a wall = 12×8 days
∴ Time taken by 6 men to construct a wall = 612×8 days
=16 days