8 girls and 12 boys can finish work in 10 days while 6 girls and 8 boys can finish it in
14 days. Find the time taken by the one girl alone that by one boy alone to finish the
work.
(a) 120, 130
(b) 140,280
(c) 240,280
(d) 100,120​

Answers

Answered by suhanishah8906
4

Answer:

Option 3 is correct answer...

.

.

.

Hope this helps you

.

.

.

Mark me as brainliest .

Answered by rekhadeepi2006
4

Step-by-step explanation:

The answer is (c) 240,280