8 machin con do a wok in 10 days and how long it 16 machin do it
Answers
Answered by
0
Answer:
5days
Explanation:
8 machines can do a work in 10 days
1 machine can do a work in 10×8 days
16 machines can do a work in 80÷16 days=5days