8 man do a work in 9 days.how many days 6 man will take to complete this work
Answers
Answered by
7
Hey Mate
Here is your answer in the attachment
Hope it helps
Cheers!!
Pls mark as brainliest if it helps
Here is your answer in the attachment
Hope it helps
Cheers!!
Pls mark as brainliest if it helps
Attachments:
![](https://hi-static.z-dn.net/files/d38/9d8372e3d61eb8bb938ab3ce3de96bef.jpg)
Answered by
7
hi
8 man do a work in 9 days
we have to find .how many days 6 man will take to complete this work
=> lets forman euqation
8 *9/6
=> 72/6
=>12 days44
hope it helps u
:)
8 man do a work in 9 days
we have to find .how many days 6 man will take to complete this work
=> lets forman euqation
8 *9/6
=> 72/6
=>12 days44
hope it helps u
:)