8 me n and 6 boys can finish a piece of work in one day while 2 men and 3 boys can finish it in 3 days find the time taken by one men and that one boy to finish the work
Answers
Answered by
23
Q: 8 men and 6 boys can finish a piece of work in one day while 2men and 3boys can finish it in 3days . find the time taken by 1 men and one boy to finish the work .
let 1 man's 1 day's work = x , and 1 boy's 1 day's
work = y so then ,
8x + 6y = 1 / 1 -----------(1)
2x + 3y = 1 /3 -----------(2)
multiply equation (1) by 2 and eq(2) by 8
16x + 12y = 2 ------------(3)
16x + 24y = 8/ 3 --------(4)
-----------------------------subract.(3) and (4)
- 12y = [ 2 - (8/ 3) ]
-12y = - 2/ 3
y = 2 /36 => y = 1 /18
put value of 'y' in (1) we get
8x + 6 ( 1/ 18 ) = 1/ 1=> 8x = 1 - ( 6/ 18 )
8x = ( 3 - 1 )/ 3 = 2 / 3
8x = 2/ 3 =>x = 2 / 24 => x = 1 /12
(1man + 1boy)' s 1 days work
= [ ( ( 1 × 1) /12 ) + ( (1 × 1 )/ 18 ) ]
= ( 1/ 12) + ( 1/ 18 )
= (18 + 12 )/ 216 = 30 / 216 = 1 / 7.2
therefore, 1 men and 1 boy can finish the work in 7.2 days.
let 1 man's 1 day's work = x , and 1 boy's 1 day's
work = y so then ,
8x + 6y = 1 / 1 -----------(1)
2x + 3y = 1 /3 -----------(2)
multiply equation (1) by 2 and eq(2) by 8
16x + 12y = 2 ------------(3)
16x + 24y = 8/ 3 --------(4)
-----------------------------subract.(3) and (4)
- 12y = [ 2 - (8/ 3) ]
-12y = - 2/ 3
y = 2 /36 => y = 1 /18
put value of 'y' in (1) we get
8x + 6 ( 1/ 18 ) = 1/ 1=> 8x = 1 - ( 6/ 18 )
8x = ( 3 - 1 )/ 3 = 2 / 3
8x = 2/ 3 =>x = 2 / 24 => x = 1 /12
(1man + 1boy)' s 1 days work
= [ ( ( 1 × 1) /12 ) + ( (1 × 1 )/ 18 ) ]
= ( 1/ 12) + ( 1/ 18 )
= (18 + 12 )/ 216 = 30 / 216 = 1 / 7.2
therefore, 1 men and 1 boy can finish the work in 7.2 days.
Answered by
19
8M + 6B = 1D
2M + 3B = 3D
Since both their work are the same:
(8 x 1)M + (6 x 1)B = (2 x 3)M + (3 x 3)B
8M + 6B = 6M + 9B
8M - 6M = 9B - 6B
2M = 3B
M = 1.5B
Find 1 man and 1 boy in term of boys:
1M + 1B = 1.5B + 1B = 2.5B
Find the amount of work 1 boy can do in a day:
8M + 6B = 1D
8(1.5)B + 6B = 1D
18B = 1D
B = 18D
⇒ 1 day = 1/18 of the work
Find the amount of work 1 man can do in a day:
1M = 1.5B
1M = 18D ÷ 1.5
1M = 12D
⇒ 1 day = 1/12 of the work
Find the amount of days 1 man and I boy need to complete the work:
1 day = 1/18 + 1/12 = 5/36 of the work
5/36 of the work = 1 day
1/36 of the work = 1 ÷ 5 = 1/5 day
36/36 of the work = 1/5 x 36 = 7.2 days
Answer: 1 man and 1 boy will take 7.2 days to complete the work.