8 men and 12 boy can finish a piece of work in 10 days while 6 men and 8 boys can finish it in 14 days . find the time taken by 1 man along and that by one boy along to finish the work
Answers
Answered by
1
total time taken=196 days.
nasskhan970:
no bro it is man finished work in 140 days and boy in 280 dsys
Answered by
3
Let the time taken by 1 man alone to finish the work be x days and the time taken by 1 boy alone to finish the work be y days. Then,
1 man's 1 day work =
1 boy's 1 day work =
∴8 men's 1 day work =
12 boy's 1 day work =
∵ 8 men and 12 boy together finish the work in 10 days
+= ⇒1.
Again, 6 men's 1 day work =
8 boy's 1 day work =
∵ 6 men and 8 boys can together finish the work in 14 days
+= ⇒2.
Put = X ⇒3. and = Y ⇒4.
Then 8X + 12Y= ⇒5.
6X + 8Y = ⇒6.
Multiplying (5) by 3 and (6) by 4
24X + 36Y = ⇒7.
24X + 32Y = ⇒8.
Subtracting 8 from 7
4Y =
Y=
=
y = 280
Putting Y= in 5.
X=
=
y= 140
Hence, the time taken by 1 man and 1 boy to finish the work alone are280 days and 140 days respectively.
Hope, it will help you!!
1 man's 1 day work =
1 boy's 1 day work =
∴8 men's 1 day work =
12 boy's 1 day work =
∵ 8 men and 12 boy together finish the work in 10 days
+= ⇒1.
Again, 6 men's 1 day work =
8 boy's 1 day work =
∵ 6 men and 8 boys can together finish the work in 14 days
+= ⇒2.
Put = X ⇒3. and = Y ⇒4.
Then 8X + 12Y= ⇒5.
6X + 8Y = ⇒6.
Multiplying (5) by 3 and (6) by 4
24X + 36Y = ⇒7.
24X + 32Y = ⇒8.
Subtracting 8 from 7
4Y =
Y=
=
y = 280
Putting Y= in 5.
X=
=
y= 140
Hence, the time taken by 1 man and 1 boy to finish the work alone are280 days and 140 days respectively.
Hope, it will help you!!
Similar questions