Math, asked by ok56, 1 year ago

8 men and 12 boys can do a pieces of work in 10 days while 6 men and 8 boys can finish it in 14 days find the time taken by one man and one boy to finish the work​

Answers

Answered by pallavishilpi
1

Let the part of the job done by 1 men per day be x

Let the part of the job done by 1 boy per day be y

So,

Multiply equation 1 by 3 and equation 2 by 4 to get,

From equation 3 and 4,

So the time taken by the boy to complete the job alone will be 280 days and for the men will be 140.


ok56: thank
Answered by daluckyseven2123
3

Answer:

140 days.

Step-by-step explanation:

Let the time be taken by one man to complete the work be x and time taken by one boy to complete \frac{1}{y} part of the work.

Since 8 men and 12 boys can finish a piece of work in 10 days,

\frac{8}{x}+\frac{12}{y} =\frac{1}{10} and \frac{6}{x} +\frac{8}{y}=\frac{1}{14}

Since the equations are not linear, let \frac{1}{x}=a and \frac{1}{y}=b

8a+12b=\frac{1}{10} and 6a+8b=\frac{1}{14}

Multiply the first equation by 3 and second equation by 4, we get

24a+36b-24a-32b=\frac{3}{10} and 24a+32b=\frac{2}{7}

Subtract the equations obtained.

24a+36b-24a-32b=\frac{3}{10}-\frac{2}{7}

4b=\frac{1}{70}b=\frac{1}{280}

Substitute in equation 8a+12b=\frac{1}{10} to obtain the value of a

8a+12(\frac{1}{280})=\frac{1}{10}a=\frac{1}{140}

So, x=\frac{1}{a}=140 and y=\frac{1}{b}=280

Hence, a man can finish the work in 140 days.


ok56: thank u so much
daluckyseven2123: no problem :)
Similar questions