8 men and 12 boys can do a pieces of work in 10 days while 6 men and 8 boys can finish it in 14 days find the time taken by one man and one boy to finish the work
Answers
Let the part of the job done by 1 men per day be x
Let the part of the job done by 1 boy per day be y
So,
Multiply equation 1 by 3 and equation 2 by 4 to get,
From equation 3 and 4,
So the time taken by the boy to complete the job alone will be 280 days and for the men will be 140.
Answer:
140 days.
Step-by-step explanation:
Let the time be taken by one man to complete the work be x and time taken by one boy to complete part of the work.
Since 8 men and 12 boys can finish a piece of work in 10 days,
⇒ and
Since the equations are not linear, let and
⇒ and
Multiply the first equation by 3 and second equation by 4, we get
and
Subtract the equations obtained.
⇒
Substitute in equation to obtain the value of
⇒
So, and
Hence, a man can finish the work in 140 days.