Math, asked by rkanmani003, 10 months ago


. 8 men and 12 boys can finish a piece of work in 10 days. While 6 men and 8
boys can finish it in 14 days. Find the time taken by one man alone and that
by one boy alone to finish the work.​

Answers

Answered by jamadarjivan01
2

Answer:

Step-by-step explanation:

Suppose,one man and boy doing work above xdays and y days .

8x+12y=10

6x+8y=14

That you can solve that by comparing to ax+by=c

Attachments:
Answered by renuagrawal393
12

 \huge{\bold{\underline{\underline{answer}}}}

let 1 man finish the work in 'x' days and

1 boy finish the work in 'y' days

when 1 man work complete work in 'x' days

then 8 man work in

 \frac{8}{x} days

when 1 boy complete work in 'y' days

then 12 boy complete work in

 \frac{12}{y} days

our equation is:-

 \frac{8}{x}  +  \frac{12}{y}  =  \frac{1}{10}

similarly, in second case

 \frac{6}{x}  +  \frac{8}{y}  =  \frac{1}{14}

let \:  \frac{1}{x} to \: be \: \bold{ a }\: and \:  \frac{1}{y} to \: be \:  \bold{b} \\ so \: that \\ 8a + 12b =  \frac{1}{10}  \\  \\  => 80a + 120b = 1...... {eq}^{n} 1 \\

6a + 8b =  \frac{1}{14}  \\ 84a + 112b = 1..... {eq}^{n} 2 \\ \:  after \: elimination \: u \: will \: get \: values \: of \: x \: and \: y \: which\: are \: ur \: answer. \\ hope \: it \: helps \: u....

Similar questions