8 men and 12 boys can finish a piece of work in 10 days while 6 men and 8 boys can finish the work in 14 days. find the time taking by 1 man alone and 1 boy alone to finish the same work. Solve using elimation method
Answers
Answer:
Step-by-step explanation:
Solution :-
Let the work done by 1 men in 1 day be x.
And the work done by 1 boy in 1 day be y.
According to the Question,
⇒ 8x + 12y = 1/10 ..... (i)
⇒ 6x + 8y = 1/14 .....(ii)
Multiplying Eq (i) with 2 and Eq (ii) with 3, we get
⇒ 16x + 24y = 1/5 ....(iii)
⇒ 18x + 24y = 3/4 .....(iv)
Subtracting Eq (iii) and (iv), we get
16x + 24y = 1/5
18x + 24y = 3/4
___________
- - -
⇒ - 2x = 1/5 - 3/4
⇒ - 2x = 14 - 15/70
⇒ - 2x = - 1/70
⇒ x = 1/140
Putting x's value in Eq (i), we get
⇒ 8x + 12y = 1/10
⇒ 8(1/140) + 12y = 1/10
⇒ 12y = 1/10 - 8/140
⇒ 12y = 14 - 8/140
⇒ 12y = 6/140
⇒ y = 1/280
Hence, 1 one men will complete the work in 140 days and 1 boy will complete the work in 280 days.
Answer:
Let the Strength of 1 man be M and Strength of 1 Boy be B.
- Ratio of Strength of Boy to Man is 1 : 2.
- That's why Ratio of Time will be 2 : 1 of Boy to Man.
- Now we will use this Ratio in Above Equation to find Days.
⠀
- As Ratio of Time of B : M = 2 : 1
- That's why we can use it as :
⠀
- This is Ratio Method, As Elimination Method is already Solved Above.