Math, asked by thelegend43, 7 months ago

8 men and 12 boys can finish a piece of work in 10 days while 6 men and 8 boys can finish it in 14 days find the time taken by one man alone then by one boy alone to finish the work what value are depicted in this question ​

Answers

Answered by kritikasharma12212
2

Answer:

HI MATE

HERE'S THE ANSWER

Step-by-step explanation:

Let the time taken by man be x days

time taken by boys be y days

work done by 1 man in one day=1/x

work done by 1 boy in one day=1/y

8/x+12/y = 1/10............eq 1

6/x+ 8/y = 1/14..........eq2

Let u=1/x & v=1/y

8u+ 12y=1/10.........eq3

6u+8v= 1/14...........eq4

Multiplying eq3 by 2 & eq4 by 3

16u+ 24y=2/10.........eq5

18u+24v= 3/14.........eq6

subtract eq 5 & 6

-2u= -3/14+2/10

-2u = (-3×10 +2×14)/140

-2u=( -30+28)/140

-2u=-2/140

u=1/140

put this value in eq 5

16u+ 24y=2/10

16×1/140 +24y =1/5

4/35+24y= 1/5

24y= 1/5-4/35

24y= (1×7 -4)/35

24y = (7-4)/35

24y= 3/35

y= 3/35×24

y= 1/280

u=1/x

1/140 = 1/x

x=140

v=1/y

1/280 = 1/y

y=280

A man complete the work in 140 days

A boy can complete the work in 280 days

HOPE IT WILL HELP YOU

PLEASE MARK AS BRAINLIST

Answered by tnwramit1
2

Answer:

Given

8M+12B can finish the work in 10 days

Whether

6M+8B can finish the same work in 14 days

So as we know work in same in both the cases

W1=W2

SIMILARLY

(8M+12B) X 10 = (6M+8B)X14

80M+120B= 84M+112B

120B-112B=84M-80M

8B=4M

M= (8/4)M

1M=2B

it means work done by one man = work done by 2 boys

Total work done by only one boy = (8M + 12B) X 10

8M=16B

(16B+12B)X10

=280days

Total work done by only one man=

(8M+6M)X10

=14MX10

=140days

Step-by-step explanation:

(Men power x time = work done)

Similar questions