Math, asked by Simrankhan0506, 1 year ago

8 men and 12 boys can finish a piece of work in 10 days while 5 men and 8 boys can finish if in 14 days. Find the time taken to finish the work by one man alone.


Omnamhashivay: 70 is the answer?

Answers

Answered by ayush824
0
answer is can't determined bcoz of negative value is coming

Simrankhan0506: Plz solve it
ayush824: can not determined
ayush824: ans can not find bcoz of minus value
Omnamhashivay: yes
Answered by Omnamhashivay
1
70 is the answer i m getting....
The method is correct!
Attachments:

ayush824: answer is can not determined
Omnamhashivay: may be bcz minus value is coming...!
ayush824: ya answer will be none of these......