8 men and 12 boys can finish a piece of work in 10 days while 6 men and 8 boys can finish it in 14 days find the time taken by one boy alone to finish the work
Attachments:
Answers
Answered by
7
8 men and 12 boys finished the work in 10 days
8M + 12B = 10D
6 men and 8 boys finished the work in 14 days
6M + 8B = 14D
.
Since both statements are referring to the same work:
(8 x 10)M + (12 x 10)B = (6 x 14)M + (8 x 14)B
80M + 120B = 84M + 112B
84M - 80M = 120B - 112B
4M = 8B
1M = 2B
.
Substitute 1M = 2B into 8M + 12B = 10D:
8(2B) + 12B = 10D
16B + 12B = 10D
28B = 10D
.
28 Boys take 10 days to finish the work.
⇒ 1 Boy will need (28 x 10 = 280) days to finish the work.
.
Answer: 1 boy will take 280 days to finish the work.