CBSE BOARD X, asked by alligation3948, 1 year ago

8 men and 12 boys can finish a piece of work in a 5 drill 6 men and 8 boys can finish it in 7 days find the time taken by one man a longer please finish the work

Answers

Answered by psea731
0

A man takes 70 days