Math, asked by nidharshansubu, 5 months ago

8 men and 4 boys can finish a piece of work in 5 days. 6 women and 8 boys can
finish the same work in 5 days.Also,4 men and 6 women can finish the same
work in 5 days .In how many days can 2 men, 3 women and 10 boys finish the
same work at their double efficiency?​

Answers

Answered by najamakhtar6291
3

Step-by-step explanation:

Let W denotes the whole given work.

Let a, b & c denote the numbers of days in which 1 man, 1 woman & 1 boy respectively can complete the whole work W by working alone.

Hence in 1 day by working alone, 1 man, 1 woman & 1 boy can complete the amounts of work respectively W/a, W/b & W/c.

It is mentioned that

(i) 4 men and 2 boys together can complete the whole work W in 5 days. So we get the following relation,

5*[4*(W/a) + 2*(W/c)] = W or 4/a + 2/c = 1/5 …… (1a)

(ii) 3 women and 4 boys together can complete the whole work W in 5 days. So we get the following relation,

5*[3*(W/b) + 4*(W/c)] = W or 3/b + 4/c = 1/5 …… (1b)

(iii) 2 men and 3 women together can complete the whole work W in 5 days. So we get the following relation,

5*[2*(W/a) + 3*(W/b)] = W or 2/a + 3/b = 1/5 …… (1c)

From (1a) + (1b) + (1c), we get,

6/a + 6/b + 6/c = 3/5 or 1/a + 1/b + 1/c = 1/10 …… (1d)

Let D denotes the time (in days) that 1 man, 1 woman and 1 boy together will take to complete the whole work W. So we get the following relation,

D*[1*(W/a) + 1*(W/b) + 1*(W/c)] = W

D*(1/a + 1/b + 1/c) = 1 or D/10 = 1 [from (1d)]

D = 10 (days) [Ans]

Hope.my review was helpful

Mark me as brainlist

Answered by rinayjainsl
1

Answer:

2 men,10 boys and 3 women will take 2.5 days to complete the work at their double efficiency

Step-by-step explanation:

Let the work done by 1 man,1 boy and 1 woman in 1 day be the following respectively

 \frac{1}{p} , \frac{1}{q} , \frac{1}{r}

Given that 8 men and 4 boys can finish a piece of work in 5 days.Therefore,work done in 1 day can be written as

 \frac{8}{p}  +  \frac{4}{q}  =  \frac{1}{5}   \\ =  >  \frac{2}{p}  +  \frac{1}{q}  =  \frac{1}{20}  -  -  > ( 1)

Similarly 6 women and 8 boys can finish the work in 5 days.Hence

  =  > \frac{6}{r}  +  \frac{8}{q}  =  \frac{1}{5}  \\  =  >  \frac{3}{r}  +  \frac{4}{q}  =  \frac{1}{10}  -  -  > (2)

4 men and 6 women can finish the work in 5 days.Hence,

 \frac{4}{p}  +  \frac{6}{r}  =  \frac{1}{5}  \\  =  >  \frac{2}{p}  +  \frac{3}{r}  =  \frac{1}{10}  -  -  > (3)

Subtracting equation 1 from equation 3,we get

(3) - (1) =  > ( \frac{2}{p}  +  \frac{3}{r} ) - ( \frac{2}{p}  +  \frac{1}{q} ) \\  =  \frac{1}{10}  -  \frac{1}{20}  =  \frac{1}{20}  \\  =  >  \frac{3}{r}  -  \frac{1}{q}  =  \frac{1}{20}  -  -  > (4)

Subtracting equation 4 from 2,we get

(2) - (4) =  > ( \frac{ 3}{r}  +  \frac{4}{q} ) - ( \frac{3}{r}  -  \frac{1}{q} )  \\  =  \frac{1}{10}  -  \frac{1}{20}  =  \frac{1}{20}  \\  =  >  \frac{5}{q}  =  \frac{1}{20}  \\  =  > q = 100

It means that 1 boy completes work in 100 days

Substituting value of q in equation 1,we get

 \frac{2}{p}  +  \frac{1}{100}  =  \frac{1}{20}  \\  =  >  \frac{2}{p}  =  \frac{1}{25}  =  > p = 50

It means that 1 man can complete the work in 50 days.Substituting q in equation 2,we get

 \frac{3}{r}  +  \frac{4}{100}  =  \frac{1}{10}  \\  =  >  \frac{3}{r}  =  \frac{6}{100}  =  > r = 50

It means that 1 woman can complete the work in 50 days.Now as the efficiency is doubled,the days of work are halved hence

p'=25\\q'=50 \\r'=25

Now 2 men,3 women and 10 boys can complete the work in

  \frac{1}{\frac{2}{p'}  +  \frac{10}{q'}  +  \frac{3}{r'} }  \\  = \frac{1}{  \frac{2}{25}  +  \frac{10}{50}  +  \frac{3}{25} }  =   \frac{1}{\frac{4 + 10 + 6}{50}}   =  \frac{50}{20}  \\  = 2.5 \: days

Therefore,2 men,10 boys and 3 women will take 2.5 days to complete the work at their double efficiency

#SPJ2

Similar questions