8 men and 6 boys can do a work in 25 days 10 nen and 15 boys can do it in 16 days.How many days will 1 man and 1 boy take to finish?
Answers
Answered by
1
8 men or 12 boys ( according to question)
I can write 8 men = 12 boys
1 man= 12/8 boys
1 man = 3/2 boy( this is how we have to transform men into boy or boy into man)
“6 men and 6 boy”
So,6 × 3/2 boy + 6 boy ( as 1 man = 3/2 boy)
9 boy + 6 boy = 15 boy
For this type of math we have a very famous MDH formula
Man × day ×hours / work = man2 × day2× hours 2 / work2
Here we know only boys (or man) and day so,
12×20=15 ×day
Day= 12×20/15
Day= 16
( Hope it helps)