8 men can build a wall in 28 hours, how many men will be
required to do the same work in 16 hours?
Answers
Answered by
1
:28×8/16
:28/2
:14
Therefore 14 men required
Answered by
1
Answer:
8 men worked for 6 days,
Work done= Rate x Time
Work done = 8M x 6 =48 M
The same work is done by 12 men with the rate of 12M
Work done = Rate x Time
48M = 12M x Time
48 = 12 x Time
48/12 = Time
4 = Time
4 days
it is related to your questions
answer
16/28×8
14 men