8 men can complete a work in 10 days. after 5 days of work 4 men leave. in how many days will the remaining men complete the work
Answers
Answered by
2
SEE,
NO OF MENS : 8 8-4=4
DAYS TAKEN : 10 x
so, x1×y1 = x2×y2
so 8×10 = 4×x
so, 8×10/4 = 20 days
So , they will complete in 20 days