8 men can do a job in 12 days . how many men will be required to do the same job in 16 days?

Answers

Answered by ritaarjun335
1

Step-by-step explanation:

8 men =12days

x men =16 days

cross multiply

8(16)=x(12)

x =  \frac{8 \times 16}{12}  =  \frac{32}{3} \: days \: or \:  {10} \frac{2}{3} days