8 men can do a piece of work in 10 days. How long will 10 men take?
a) 12days
b) 8 days
c) 7days
d)6days
(Correct answer will marked as brainlist )
Answers
Answered by
4
Given:
- 8 men can do a work in 10 days.
To find:
- How long will 10 men take to do same work
Solution:
According to the given question,
8 men take to do a piece of work = 10 days
∴ 1 men take to do same work = 10 × 8 = 80days.
Now,
We found that 1 men can do that work in 80 days.
∴ 10 men take to do same work =
Hence,
10 men will take 8 days to complete same work.
Therefore,
option 'b' is correct.
Answered by
0
Answer:
8 days is the correct answer for this problem