8 men can do a piece of work in 15 days, how many men do it in 10 days?

Answers

Answered by mahesh01082003
4
15 × 8 = 120
Hence,
10 × men = 120
men = 120/10
men = 12

Ans: 12 mens can do a piece of work in 10 days.

HOPE IT HELPS
PLEASE GIVE 5 STARS

mahesh01082003: Hiii...
mahesh01082003: Please give 5 stars
shirad: l give you 5 stars
Answered by princess108
1
Heya friend here is your ans
8 men = 15 days
1 men = 8 * 15 = 120days
10 days = 120 diveded by 10=12..


hope it helped you
please mark me as brainlist
follow me

princess108: please mark me as brainlist
mahesh01082003: Your answer is not perfect
mahesh01082003: How can anybody will give 5 stars
princess108: but it can be understood
mahesh01082003: method is not proper