8 men can do a piece of work in 15 days. Let's find in bhow many days will men finish the same work
Answers
Answered by
2
8 men can do a piece of work in 15 days
1 man can do a piece of work in 15×8 days
10 men can do a piece of work in 15×8/10 days = 12 days
10 men do the same work in 12 days
hope it helpful for you.