Art, asked by neenajamessahu, 3 months ago

8 men can finish a piece of work in 40 days. If 2 more men join them ,the work will be completed in


Answers

Answered by dhartimasrani
5

Answer:

20 days

Explanation:

hope its helpful to uu

Answered by Adityaabanve
0

Answer:

First division of 40/8 = 5

each men can finish the a piece of work in 5 days.

if tow men are added = 8+2 = 10

second division is - 10/40 = 4

now . each men can finish a piece of work in 4 days

than the work will finish in 20Day

Similar questions