8 men can finish a piece of work in 40 days. If 2 more men join them, the work will be completed in ____. Pls explain too​

Answers

Answered by kanvi14
7

Kindly refer the attachment

Attachments:
Answered by ravisankarmory
2

Answer:

8 men  take 40 days to finish

If two more men join then total number of men =  10 

8 men finish the work in =40 days

1 man will finish the work in =40×8days          [1 man will take longer to finish the work that's why we use multiplication]

10 men will finish the work in =1040×8=32 days                [10 man will finish the work faster that's why we use division]